Boardwalk Timber Reconstruction Project

Bid receipt date: September 14, 2022
Bid award date: September 21, 2022
Construction start date: On or about October 17, 2022
Construction end date: On or about 60 days following construction start date

Area 1:  Grant Avenue vehicle ramp and boardwalk
Street end/vehicle ramp to the boardwalk will be closed for the entire duration of the project and is the designated construction staging area. Vehicle ramp will be reconstructed. The boardwalk east of the vehicle ramp will be reconstructed in two phases so that pedestrian access is available at all times north/south through the Casino Pier. 

Area 2: Dupont Avenue northbound to Franklin Avenue - terminus of the project is dependent upon final contract award amount and available funding. There may be funding to advance the project northbound past Franklin Avenue toward Hamilton Avenue. Pedestrian access north/south will be maintained during the project with potential intermittent disruptions.  Emergency vehicle access across the dune to the beach will be provided via the Franklin Avenue vehicle crossover.

Questions should be directed to the Borough Administrator.  administrator@seaside-heightsnj.org